Primavera P6 R8.1

Posted on by

Before starting this topic, one must have working knowledge of the following topics in the Enterprise Project Management Software, P6. How to define Resources in Primavera Project Planner P6 R8.1? (Part 2 of 2) Read:::: How to define Resources in Primavera Project Planner P6 R8.1?

Primavera P6 Software DownloadFree Download Primavera P6 R8.4

How to Set Default Settings for a Project in Primavera Project Planner P6 R8.1? We can set some default settings in P6. So when we will create new project, these default settings will be applied.

The settings for which we can set the default values include Duration Type, Percent Complete Type, Activity Type, Activity ID Prefix, Activity ID Suffix, Increment, Cost Account and Calendar. Whenever a user creates a project, P6 takes the default values for the above mentioned parameters. Cristiano Ronaldo Moments Pdf. A user can make its job very easy if he is wise in selecting the default values. Let us understand this by a simple example.

A Scheduler is entering (or importing) 2000 activities for which he has to “5-Working Days per week”. If the default value for calendar is set previously to “ 7-Working Days Per Week” then the Scheduler has to change the calendar for all the 2000 activities. Therefore, to avoid such overwork, he (the Scheduler) can set the default value of calendar to “ 5-Working Days per Week” and then enter (or import) the activities.

This little step (setting the default values) will make the calendar “ 5-Working Days Per Week” assigned to all of the activities automatically. It is important to note that the default values or settings affects only new activities and have no effect on previously entered activities.

The default settings for a project can be entered in the Default Tab of the Project Details. Click on Projects Icon in the Directory tool bar or click on Enterprise >Projects. This will open the Projects Window. “Defaults” Tab in Project Details in P6 R8.1 The Activity ID Prefix shows the values of Prefix when and activity is added. In an Activity ID “ABC000”, “ABC” is the Activity ID Prefix while “000” is the Activity ID Suffix. Keep a reasonable increment so that extra activities within two activities can be added.

If “Increment Activity ID based on selected activity” is checked then New Activity ID will be depending on the Activity ID selected before the addition of new activity. Let us understand this by a simple example; Consider we have two activities having Activity IDs “ABC0010” and “ABC0050”. Let us consider that the above said check box is checked and increment is 10. Then if you select “ABC0010” and you add new activity, the Activity ID of the new Activity will be “ABC0020”. Similarly if “ABC0050” is selected and a new activity is added, the new activity will be having Activity ID “ABC0060”.

Getting the right versions of browser and java runtime environment on your PC is critical when using Oracle Primavera P6 EPPM web client. If you’re experiencing difficulties, you may not have the correct combinations of web browser or Java installed. At Ten Six, we’ve been running some tests to find out what combination of recent browser and Java releases work well with Primavera P6 EPPM R8.1 and can now provide you with some technical tips and downloads to help you install a robust combination. Common Problems with Primavera P6 EPPM R8.1 Web Client When you don’t have the right version of Browser or Java on your machine, you may experience some or all of the following issues: • Poor performance when changing from one page to another takes 30 seconds or more, when it should take less than 5 seconds. This may be accompanied by the PCs internal cooling fan starting up during page changes indicating the machine is thrashing the CPU. • Popup list dialogs open but fail to populate with data.

• Graphical charts fail to load in certain portlets and in the Resources tab. • When projects are being copied or exported the browser boots you out of the program with a time-out error and loads the login screen.

The Solution Let’s start with an excerpt from the officially supported browser and java versions as published in the Primavera Tested Configurations document for Primavera P6 EPPM R8.1. Oracle Primavera P6 EPPM R8.1 Tested Configurations The above are a subset of the supported configurations from Primavera for the most commonly used client systems. For the full list, download the Oracle Primavera Tested Config R8.1.xls document. The above configurations were published by Oracle Primavera in September 2011. With the speed at which new browsers and Java versions are being released, it’s hardly surprising that these tested configurations are somewhat behind the curve. We’ve been testing the newer versions and have found that the following combinations work well with Primavera P6 EPPM R8.1. Ten Six Tested Browsers and Java Browser Specifics The following browsers were tested with P6 in Windows 7 and Windows XP (SP3) with Java 6 Update 27 installed.